![]() |
|
San
Lorenzo, CA
|
(510)276-4700
|
www.oroloma.org
|
Spring 2003
|
Issue 31
|
|
Construction on the Oro Loma Sanitary District Wastewater Treatment Plant
Capacity Restoration Project began July 19, 2004. The historic $34 million
project is scheduled to be completed on April 15, 2007, a period of 1,000
days. The project is funded entirely by Oro Loma through cash reserves
accumulated over years of sound fiscal planning. Bar Screen As wastewater flows down a main channel to the plant, it passes through
a screen that removes large objects that could damage the plant's pumps
and other equipment. Oro Loma now has one screen. As part of the restoration
project, a second channel and screen will be added. Excavation for that
channel is now complete. Chemically Enhanced Primary Treatment (CEPT) Primary treatment of wastewater involves a process in which solids are allowed to settle out of the wastewater stream. Oro Loma is adding a procedure to help hasten the process. The CEPT process
involves the injection of ferric chloride into the incoming wastewater
stream. The chemical creates a gelatin-like substance that helps the settling
of solids. The foundation and walls of the CEPT facility are completed
and the chemical tanks are in place. Digester Heating Building
Pile Driving Since the Oro Loma wastewater treatment facility is built on the shore
of San Francisco Bay, care must be taken to ensure the stability of any
new construction. To accomplish this, 1,100 friction piles will be driven
into the soil. These piles, which will be driven to a depth of between
40 and 60 feet, will support the boiler building, the three new clarifiers,
and two new pump stations. Pile driving began on November 8 and will continue
for two to three months. |