|

Construction of Oro Loma's historic $34 million plant capacity restoration
project remains on-time and on-budget. Below is a summary of major achievements
so far.
Bar-screens: The first of the two new bar-screens that will replace the
present single screen is in its final testing stage. The new channel has
been built; the screen has been installed; and the electrical hook-ups
are complete. The old screen should be out and the new one running by
the end of May.
Influent Pump Station: Wastewater travels mainly by gravity to the treatment
plant. Once at the plant, the water must be lifted so that it can again
flow by gravity through the plant. At present, Oro Loma has four pumps
that can lift over 100 million gallons of water a day. Since the plant
only processes an average 16.5 million gallons of wastewater per day,
it would seem these pumps are more than adequate to handle the load. The
problem is that the 16.5 million gallons is for an average dry day. When
it rains, the amount of water entering the plant goes up significantly.
This is true even though storm water is not carried directly through the
District's wastewater system. After a series of severe storms, the plant
may be required to handle up to 106 million gallons of water per day.
Federal guidelines require that the District be able to pump its highest
flows with its largest pump out-of-service. Thus, a new pump is being
added that can pump 35 million gallons of wastewater on its own. The structure
for this pump is now half completed, and the necessary 30-inch influent
piping is in place.
Chemically Enhanced Primary Treatment (CEPT): The new CEPT facility,
which will help hasten the process by which solids settle out of wastewater,
is now complete.
Digester Heating Building: The new digester heating building is complete.
The building houses a new boiler, as well as three new heat exchangers
that will efficiently maintain heating temperatures required by the digesters.
Disinfection Channel: The bottom of the expanded disinfection channel
is now complete and the walls
are under construction.
Pile Driving: Pile driving of 1,100 concrete piles is now complete and
excavation on the new secondary clarifiers can begin.
New Secondary Clarifiers: This is the most time-consuming component of
the restoration project.
One of the last stages of the wastewater treatment process, before the
treated water is chlorinated and sent for discharge into the San Francisco
Bay, involves the secondary clarifier tanks. Here the last of the solids
are separated out of the wastewater stream. At present, Oro Loma has three
tanks that are rectangular in shape, each with a 90-foot diameter treatment
area; they are 9-feet deep. These clarifiers no longer meet modern treatment
standards, and they will be replaced by three 120-foot diameter round
clarifiers that are 18-feet deep. The work on the 700 piles required by
the new clarifiers has been completed, and excavation for the tanks has
begun.
|