![]() |
|
San
Lorenzo, CA
|
(510)276-4700
|
www.oroloma.org
|
Spring 2006
|
Issue 39
|
|
Plant Restoration Project The ambitious plant restoration project that Oro Loma and Castro Valley
(which owns25% of the District's All three new circular clarifiers, which have a diameter of 120 feet
and a depth of 18 feet, are complete. The new disinfection channel and
connection to the existing disinfection channel are all complete. This
new channel system more than doubles Oro Loma's disinfecting capabilities
and allows the District to shut down one channel or the other for maintenance
and repair. The massive new pump station still needs some electrical work and piping.
This should be finished by April of this year. Then extensive testing
of the plant will begin. Testing will be carried out in two phases-operation
and stress testing. The District anticipates that the newly restored plant
will be fully functional and online by this summer. An open house to celebrate
the successful completion of this historic project is planned for fall
2006 or spring 2007. Look for details in upcoming newsletters.
Despite encountering unforeseen obstacles 10-50 feet below the surface,
and a water table that is only 7-8 feet below the surface, Monterey Mechanical
continued to work without delay. When challenged with the need to shut
down half of the existing disinfection channel, they worked 10 hours a
day, six days a week for seven weeks to create a 48-inch pipe bypass that
allowed them to complete work on the new channels in record time. When complete, the plant will produce treated discharge that meets stringent
environmental standards well into the future, both in dry and in wet weather. |